- First pad drilled for a new customer on an 8-well program
- Ended the well program at 9.36 days under the operator’s AFE
- Saved the equivalent total time of one well
Working together to deliver better drilling outcomes
Planning and Preparation
Meticulously organized strategies focused on achieving the operator’s performance goals
Field-Proven Technology
H&P’s FlexFusion technology package enhanced consistency and reduced flat time
Seamless Collaboration
Customer, rig crews, on-site leadership and remote support teams openly discussed best practices, lessons learned, and recommendations to help ensure optimal performance
Continuous Communication
Ongoing feedback loop between all parties throughout the entire operation